Project Description 

As our infrastructure continues to age, we proactively replace water mains to ensure safe, reliable, high-quality water service to our community with superior service. WaterOne replaced an existing 12” cast iron pipe (1960 – 1966) with 16” PVC water main along Switzer Road between 91st Street and 95th Street. This project was in coordination with the City of Overland Park Street and Storm Sewer Improvement Project, which began August 2014. WaterOne's work began October 2014, and this project was completed in March 2015.

 

Project Update
Construction Start October 2014
Construction End March 2015
Cost $700K
Project Phase Completed