Pipeline Project - 199th St from Quivira to Metcalf

Print
100% Completed
Laying Pipe


WaterOne Project Manager
Josh Vincent
913/895-5766

Project Description

In order to strengthen our infrastructure in our southern service area, we are installing a 20-inch main (pipeline) along 199th Street from Quivira to Metcalf. Once completed, the project will improve reliability of water supply in southern Johnson County by improving the flow between WaterOne's elevated tank at 199th Street & Lackman and WaterOne's pump station at 211th Street & Metcalf. 

There should be minimal disruption in the area during the installation of the new mains, but we will make an effort to give customers advance notice of service interruptions through Notify JoCo. To ensure that we can reach you with water alerts, sign-up at www.NotifyJoCo.org and customize your contact preferences by tagging locations of your home, work, school, etc. If you need assistance signing-up for NotifyJoCo, contact 913/826-5555.

Project Update
Project Phase In Construction
Construction Start Spring 2015
Construction End January 2016
Cost $3.0M